New build snagging checklist (UK, 2026)

What to check outside and in every room, the NHBC tolerances builders work to, when you have the right to inspect, and how to record each snag so it gets fixed first time.

By ARX Algorithms, makers of SnagAudit · Updated 1 October 2026

What snagging is, and why it pays to do it properly

A snag is anything in a new or refurbished home that is unfinished, damaged or not built to the expected standard: a paint run, a door that sticks, a cracked tile, missing mastic round a bath, a gutter that drips. Snagging is the walk-round that finds them, records each one clearly and hands the list to the builder to put right.

New homes are rarely perfect. One widely reported industry figure put the average at 157 snags per new-build home (BuildScan, reported in 2021, up from 80 in 2005). Most are small. The point of a good snag list is that every one of them is described precisely enough, and photographed well enough, that nobody can argue about what was meant or whether it was there before.

When to snag: your rights before and after completion

Most new homes in England are built by developers signed up to one of two consumer codes, and both give you a chance to inspect before you complete.

In short: snag before completion if you can, snag again in the first few weeks of living there, and do a final check before the end of year two.

What "acceptable" looks like: NHBC tolerances

Whether something is a snag often comes down to a measurement. NHBC's Standards (Chapter 9.1, "A consistent approach to finishes", 2024 edition) set out what most warranty providers and developers accept. Finishes are judged from about 2 metres away in normal daylight, not with a torch held against the wall.

ElementNHBC tolerance
Internal walls, plumbUp to 8 mm out of plumb for walls up to 3 m high
Internal walls, flatness±3 mm under a 2 m straight edge
Ceilings, levelWithin 3 mm per metre (ceilings up to 6 m across)
Ceilings, flatness±5 mm under a 2 m straight edge
Cracks at wall, floor and ceiling junctionsUp to 2 mm wide may occur through drying shrinkage
FloorsLevel within 3 mm per metre (up to 6 m across); flat within ±5 mm under a 2 m straight edge
Skirting to floor finishGap no more than 5 mm
Internal doorsGap at head and sides no more than 4 mm; 10 to 22 mm under the door to an unfinished floor
Window heads, sills and revealsWithin 3 mm for openings up to 1.5 m (5 mm if larger)
Wall and floor tilingFlat within ±3 mm over 2 m; lips between tiles no more than 1 mm (joints up to 6 mm) or 2 mm (wider joints)
GlazingViewed from 2 m (3 m for toughened or laminated glass); fine scratches up to 25 mm long acceptable if not obtrusive
External brickworkUp to 8 mm out of plumb per storey (up to 3 m); ±8 mm straightness over 5 m
PaintworkFree from conspicuous runs and prominent brush marks

Anything outside these figures is worth recording with a measurement and a photo that shows the straight edge or tape in shot. Check the current edition of the NHBC Standards if a dispute turns on a number.

The new build snagging checklist

Work methodically: outside first while the light is good, then room by room, top floor down, clockwise round each room. Look at every surface, open and close everything, and run every tap and appliance.

Outside

Every room

Kitchen

Bathrooms and en-suites

Loft, stairs and services

How to record a snag so it gets fixed first time

  1. Number it so everyone refers to the same item.
  2. Say where it is: room, wall, height. "Bedroom 2, window wall, left of the window, about 1.2 m up."
  3. Describe the defect, not the cause: "Hairline crack in the plaster, 300 mm long." Leave the diagnosis to the builder.
  4. Photograph it from close up and from far enough away to show where it is, and draw an arrow on the photo.
  5. Name the trade (plasterer, decorator, plumber) so it goes to the right person.
  6. Date everything, then re-inspect and close each item with an "after" photo.

That is exactly the workflow SnagAudit's snagging app is built around: one item per snag, photos with mark-up, trade and status, and a numbered PDF snag list you can hand over before you leave the site.

Sources

Questions

When should I do a snagging inspection on a new build?

Before completion if the developer allows it, and both main consumer codes say they must offer you the chance: under the New Homes Quality Code and the Consumer Code for Home Builders you can inspect, or send a professional, after the notice to complete and before legal completion. Snag again in your first weeks in the home and before the end of the two-year builder warranty period.

How many snags does a typical new build have?

A widely reported industry figure put the average at 157 snags per new home (BuildScan, 2021). Most are cosmetic, such as paint runs, sealant gaps and door adjustments, but each one is worth recording with a photo.

Can I use an app for the NHQB pre-completion inspection?

The New Homes Quality Code allows the NHQB pre-completion checklist to be completed digitally, as long as it carries out the same checks as the official template. A snagging app is ideal for recording, photographing and sharing everything you find alongside it.

What tolerances do builders work to?

Most UK developers and warranty providers follow NHBC Standards Chapter 9.1. For example, internal walls should be flat within plus or minus 3 mm under a 2 m straight edge, and the gap under skirting should be no more than 5 mm.

Who fixes snags after I move in?

Under NHBC Buildmark, the builder is responsible for putting right defects reported in the first two years. Report them as soon as you find them, in writing, with photographs.